KINGS PARK SEWER CONSTRUCTION - SCHEDULE UPDATE #4 (11/06/23 - 11/27/23)

The Contractor is continuing installation on Yale Place and Bowman Lane. From Bowman installation will be progressing on Squire Lane and onto St. Johnland Road. During working hours a detour has been established. Please note local traffic and buses will still have access to roadway as needed.

 

Please note there will be now work occurring the week of November 20th. 
 
You can expect periodic inconvenience due to equipment movement, material transport and trench excavation. There may be periodic road/lane closures and detours as well as elimination of parking spaces along roadway during construction, however, every effort will be made to minimize disturbances. Access to driveways may be obstructed for certain work, in these cases advanced notice will be provided. Noise from construction equipment can be expected during working hours (7:00 am – 3:30 pm). 

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

KINGS PARK SEWER CONSTRUCTION - SCHEDULE UPDATE #3 (10/23/23 - 11/03/23)

The Contractor will continue to progress installation North on Lawrence Road between Boxwood Drive and Yale Place. During working hours a detour has been established. Please note local traffic and buses will still have access to roadway as needed.

 
You can expect periodic inconvenience due to equipment movement, material transport and trench excavation. There may be periodic road/lane closures and detours as well as elimination of parking spaces along roadway during construction, however, every effort will be made to minimize disturbances. Access to driveways may be obstructed for certain work, in these cases advanced notice will be provided. Noise from construction equipment can be expected during working hours (7:00 am – 3:30 pm). 

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

KINGS PARK SEWER CONSTRUCTION - SCHEDULE UPDATE #2 (10/09/23 - 10/20/23)

Please note there will be no work in roadway on Monday 10/09 in observance of Columbus Day. Force main installation will continue on Tuesday 10/10. The Contractor will continue to progress installation North on Lawrence Road between 25A and Boxwood Drive.

 
You can expect periodic inconvenience due to equipment movement, material transport and trench excavation. There may be periodic road/lane closures and detours as well as elimination of parking spaces along roadway during construction, however, every effort will be made to minimize disturbances. Access to driveways may be obstructed for certain work, in these cases advanced notice will be provided. Noise from construction equipment can be expected during working hours (7:00 am – 3:30 pm). 

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

KINGS PARK SEWER CONSTRUCTION - SCHEDULE UPDATE #1 (9/25/23 - 10/06/23)

Starting on Tuesday 9/26 through Wednesday 9/27 the Contractor will begin saw cutting the roadway on Lawrence Road, Bowman Lane,  and Yale Lane  between 25A and St. Johnland Road. On Thursday 9/28 the Contractor will begin excavation work for force main installation. Installation will begin just North of the Intersection of Lawrence Road and NY-25A and will continue up to Boxwood Drive. This segment of force main is estimated to be completed by Friday, 10/6. 
 
You can expect periodic inconvenience due to equipment movement, material transport and trench excavation. There may be periodic road/lane closures and detours as well as elimination of parking spaces along roadway during construction, however, every effort will be made to minimize disturbances. Access to driveways may be obstructed for certain work, in these cases advanced notice will be provided. Noise from construction equipment can be expected during working hours (7:00 am – 3:30 pm). 

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

THE KINGS PARK SEWER EXPANSION

Suffolk County and the Town of Smithtown are thrilled to announce that the highly anticipated sewer line construction into Downtown Kings Park is set to break ground in the Summer of 2023. 

 

The installation of sewers in Downtown Kings Park, will make way for new or expanded commercial growth like restaurants, cafes, bars, and mixed use development. Furthermore, as we’ve historically witnessed in surrounding areas, the project will increase property values within the community. 

View & Download the Kings Park Downtown Sewers Phasing Map