KINGS PARK SEWER CONSTRUCTION - SCHEDULE 12/2/2024 - 12/13/2024

 ​The Contractor will be continuing roadway restoration on Town and State roadways dependent on weather conditions. They will also be testing remaining sewer lines, completing curb & sidewalk repairs and installing manhole benches. 

If you notice a pothole or other issue, please contact us at (631) 393-4994.

 

Please note that restoration of NY 25A is not complete. Finished asphalt (blacktop) surface will be installed in Spring of 2025. At this time the roadways have been temporarily patched/restored to allow for use. Upon final completion in May 2025 all impacted roads will be returned to a smooth finished surface and striped to match the pre-existing conditions before construction started.

The first segment of concrete panel replacement was completed between Church Street and Pulaski and left low. East of Church Street and West of Pulaski only temporary trench restoration has been completed and concrete panel replacement will be scheduled dependent on weather. Prior to the completion of Contract all road surfaces impacted will be repaved similar to what was completed on Church Street and Lawrence Avenue. 

You can expect periodic inconvenience due to equipment movement, material transport and trench excavation. There may be periodic road/lane closures and detours as well as elimination of parking spaces along roadway during construction, however, every effort will be made to minimize disturbances. Access to driveways may be obstructed for certain work, in these cases advanced notice will be provided. Noise from construction equipment can be expected during working hours. 

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

KINGS PARK SEWER CONSTRUCTION - SCHEDULE 11/10/2024 - 11/22/2024

 All underground gravity sewer installation has been completed. Full depth restoration of Main Street between Church Street and Pulaski is schedule for the next two weeks. This includes replacement of concrete panel road base. 

Nightwork hours will be between 8:30 pm and 6:00 am. Nightwork in 25A will occur from Sunday - Friday nights. 

If you notice a pothole or other issue, please contact us at (631) 393-4994.

You can expect periodic inconvenience due to equipment movement, material transport and trench excavation. There may be periodic road/lane closures and detours as well as elimination of parking spaces along roadway during construction, however, every effort will be made to minimize disturbances. Access to driveways may be obstructed for certain work, in these cases advanced notice will be provided. Noise from construction equipment can be expected during working hours. 

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

KINGS PARK SEWER CONSTRUCTION - SCHEDULE 10/28/2024

Plans for week of 10/28 :

 

The Contractor plans to continue installing gravity main on Indian Head Road, gravity main stubs to side streets throughout Kings Park, as well as curb and sidewalk repair to impacted areas. This work is scheduled for night time installation, 8:30 PM - 6:00 am.



Nightwork hours will be between 8:30 pm and 6:00 am. Nightwork in 25A will occur from Sunday - Thursday nights. 

If you notice a pothole or other issue, please contact us at (631) 393-4994.

You can expect periodic inconvenience due to equipment movement, material transport and trench excavation. There may be periodic road/lane closures and detours as well as elimination of parking spaces along roadway during construction, however, every effort will be made to minimize disturbances. Access to driveways may be obstructed for certain work, in these cases advanced notice will be provided. Noise from construction equipment can be expected during working hours. 

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

KINGS PARK SEWER CONSTRUCTION - SCHEDULE 10/14/2024

Plans for week of 10/14 :

 

The Contractor plans to continue installing laterals off the main sewer down 25A. This work phase will continue as previously, Sunday through Thursday nights, about 8:00 pm to 6 am, Throughout the Kings Park downtown area.  The work will involve excavation from the main line sewer pipe to the curb line.  They expect to place temporary asphalt to grade at the end of each night's work.

 

The contractor has moved the working hours of the LIRR crossing on Indian Head Road to night work, 9 pm – 5 am. The crossing is planned to conclude Friday, October 18th. Flaggers with the MTA will be present on site to allow for two-way traffic. The work zone will be secured at the end of each work period and should not significantly impact daytime traffic.

 

Nightwork hours will be between 8:30 pm and 6:00 am. Nightwork in 25A will occur from Sunday - Thursday nights. 

If you notice a pothole or other issue, please contact us at (631) 393-4994.

You can expect periodic inconvenience due to equipment movement, material transport and trench excavation. There may be periodic road/lane closures and detours as well as elimination of parking spaces along roadway during construction, however, every effort will be made to minimize disturbances. Access to driveways may be obstructed for certain work, in these cases advanced notice will be provided. Noise from construction equipment can be expected during working hours. 

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

KINGS PARK SEWER CONSTRUCTION - SCHEDULE 10/07/2024

Plans for week of 10/07 :

 

The Contractor plans to install laterals off the main sewer down 25A. This work phase will continue as previously, Sunday through Thursday nights, about 8:00 pm to 6 am, Throughout the Kings Park downtown area.  The work will involve excavation from the main line sewer pipe to the curb line.  They expect to place temporary asphalt to grade at the end of each night's work area.

 

The LIRR crossing on Indian Head Road is set to begin during daytime hours 7:00 am - 3:30 pm on 10/14 and conclude after approximately 2 weeks.

 

Nightwork hours will be between 8:30 pm and 6:00 am. Nightwork in 25A will occur from Sunday - Thursday nights. 

If you notice a pothole or other issue, please contact us at (631) 393-4994.

You can expect periodic inconvenience due to equipment movement, material transport and trench excavation. There may be periodic road/lane closures and detours as well as elimination of parking spaces along roadway during construction, however, every effort will be made to minimize disturbances. Access to driveways may be obstructed for certain work, in these cases advanced notice will be provided. Noise from construction equipment can be expected during working hours. 

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

KINGS PARK SEWER CONSTRUCTION - SCHEDULE 09/15/2024

Plans for week of 9/15 :

 

The Contractor plans to continue nighttime excavation and pipe installation in Main Street. This work phase will continue as previously, Sunday through Thursday nights, about 8:00 pm to 6 am, just past the 25A/Church Street intersection, working west towards towards Pulaski.  The work will involve excavation down the middle of Main Street for the installation of gravity sewer main pipes between the manholes, as well as lateral pipes towards curb lines.  They expect to place road plates securely in the street at the end of each night's work area.  There could be several road plates in Main Street during the daytime during the week.  Road plates are not expected to be in place over the weekend.

 

Please be aware that excavation for jacking under the LIRR on Indian Head Road is planned to begin the week of 09/30. More to come.

 

 

Nightwork hours will be between 8:30 pm and 6:00 am. Nightwork in 25A will occur from Sunday - Thursday nights. 

If you notice a pothole or other issue, please contact us at (631) 393-4994.

You can expect periodic inconvenience due to equipment movement, material transport and trench excavation. There may be periodic road/lane closures and detours as well as elimination of parking spaces along roadway during construction, however, every effort will be made to minimize disturbances. Access to driveways may be obstructed for certain work, in these cases advanced notice will be provided. Noise from construction equipment can be expected during working hours. 

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

KINGS PARK SEWER CONSTRUCTION - SCHEDULE 09/08/2024

Plans for week of 9/8 :

 

The Contractor plans to continue nighttime excavation and pipe installation in Main Street. This work phase will continue as previously, Sunday through Thursday nights, about 8:00 pm to 6 am, from the intersection of Church Street and 25A., working west towards Pulaski.  The work will involve excavation down the middle of Main Street for the installation of gravity sewer main pipes between the manholes, as well as lateral pipes towards curb lines.  They expect to place road plates securely in the street at the end of each night's work area.  There could be several road plates in Main Street during the daytime during the week.  Road plates are not expected to be in place over the weekend.

 

Please be aware that excavation for jacking under the LIRR on Indian Head Road is planned to begin the week of 09/30. More to come.

 

 

Nightwork hours will be between 8:30 pm and 6:00 am. Nightwork in 25A will occur from Sunday - Thursday nights. 

If you notice a pothole or other issue, please contact us at (631) 393-4994.

You can expect periodic inconvenience due to equipment movement, material transport and trench excavation. There may be periodic road/lane closures and detours as well as elimination of parking spaces along roadway during construction, however, every effort will be made to minimize disturbances. Access to driveways may be obstructed for certain work, in these cases advanced notice will be provided. Noise from construction equipment can be expected during working hours. 

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

KINGS PARK SEWER CONSTRUCTION - SCHEDULE 09/01/2024

Plans for week of 9/1 :

 

There will be no night work Sunday and Monday nights, Sept. 1 and 2, due to the holiday.

 

The Contractor plans to continue nighttime excavation and pipe installation in Main Street. This work phase will continue as previously, Sunday through Thursday nights, about 8:00 pm to 6 am, from in front of the KP Fire Dept., working west towards Pulaski.  The work will involve excavation down the middle of Main Street for the installation of gravity sewer main pipes between the manholes, as well as lateral pipes towards curb lines.  They expect to place road plates securely in the street at the end of each night's work area.  There could be several road plates in Main Street during the daytime during the week.  Road plates are not expected to be in place over the weekend.

The Contractor needs to compete restoration of road striping and markings on Indian Head Road, and Meadow Road.  We do not yet have a scheduled date for this.   

 

Nightwork hours will be between 8:30 pm and 6:00 am. Nightwork in 25A will occur from Sunday - Thursday nights. 

If you notice a pothole or other issue, please contact us at (631) 393-4994.

You can expect periodic inconvenience due to equipment movement, material transport and trench excavation. There may be periodic road/lane closures and detours as well as elimination of parking spaces along roadway during construction, however, every effort will be made to minimize disturbances. Access to driveways may be obstructed for certain work, in these cases advanced notice will be provided. Noise from construction equipment can be expected during working hours. 

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

KINGS PARK SEWER CONSTRUCTION - SCHEDULE 8/25/2024

Plans for week of 8/25:

The Contractor plans to continue nighttime excavation and pipe installation in Main Street. This work phase will continue as previously, Sunday through Thursday nights, about 8:00 pm to 6 am, from Patiky Street, working west towards Church Street.  The work will involve excavation down the middle of Main Street for the installation of gravity sewer main pipes between the manholes, as well as lateral pipes towards curb lines.  They expect to place road plates securely in the street at the end of each night's work area.  There could be several road plates in Main Street during the daytime during the week.  Road plates are not expected to be in place over the weekend.

 

The Contractor expects to compete restoration of road striping and markings on Church Street, Indian Head Road, and Meadow West by Tuesday of this week. 

 

Nightwork hours will be between 8:30 pm and 6:00 am. Nightwork in 25A will occur from Sunday - Thursday nights. 

If you notice a pothole or other issue, please contact us at (631) 393-4994.

You can expect periodic inconvenience due to equipment movement, material transport and trench excavation. There may be periodic road/lane closures and detours as well as elimination of parking spaces along roadway during construction, however, every effort will be made to minimize disturbances. Access to driveways may be obstructed for certain work, in these cases advanced notice will be provided. Noise from construction equipment can be expected during working hours. 

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

KINGS PARK SEWER CONSTRUCTION - SCHEDULE 8/11/2024

Plans for week of 8/11:
The Contractor plans to continue nighttime excavation and pipe installation in Main Street. This work phase will continue as previously, Sunday through Thursday nights, about 8:00 pm to 6 am, from Patiky Street, working west towards Church Street. The work will involve excavation down the middle of Main Street for the installation of gravity sewer main pipes between the manholes, as well as lateral pipes towards curb lines. They expect to place road plates securely in the street at the end of each night's work area. There could be several road plates in Main Street during the daytime during the week. Road plates are not expected to be in place over the weekend.

Final Paving of the road surface on Church Street, Indian Head Road, Meadow East and West, Stattle and Park is scheduled to start during daytime hours Monday 8/12 through Friday, depending on the weather. The intersection of Meadow and Indian Head will be paved at a later date. Paving is planned to start at the north end of Church Street, moving south to Indian Head, Meadow, Park and Stattle.

 

Nightwork hours will be between 8:30 pm and 6:00 am. Nightwork in 25A will occur from Sunday - Thursday nights. 

If you notice a pothole or other issue, please contact us at (631) 393-4994.

You can expect periodic inconvenience due to equipment movement, material transport and trench excavation. There may be periodic road/lane closures and detours as well as elimination of parking spaces along roadway during construction, however, every effort will be made to minimize disturbances. Access to driveways may be obstructed for certain work, in these cases advanced notice will be provided. Noise from construction equipment can be expected during working hours. 

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

KINGS PARK SEWER CONSTRUCTION - SCHEDULE 07/22/2024 - 08/02/2024

Final paving restoration has been completed on all of Lawrence, Bowman, Yale, Squire, and St. Johnland. No further work is planned on these roads.

 

Plans for week of 8/4:
The Contractor plans to continue nighttime excavation and pipe installation in Main Street. This work phase will continue as previously, Sunday through Thursday nights, about 8:30 pm to 6 am, from Patiky Street, working west towards Church Street. The work will involve excavation down the middle of Main Street for the installation of gravity sewer main pipes between the manholes, as well as lateral pipes towards curb lines. They expect to place one or two road plates securely in the street at the end of each night's work area.

Milling and Final Paving of the road surface from Kings Wood complex to Main Street is scheduled to start during daytime hours Monday 8/5 through Friday. Alternating one-way traffic will be maintained during this work.

 

Nightwork hours will be between 8:30 pm and 6:00 am. Nightwork in 25A will occur from Sunday - Thursday nights. 

If you notice a pothole or other issue, please contact us at (631) 393-4994.

You can expect periodic inconvenience due to equipment movement, material transport and trench excavation. There may be periodic road/lane closures and detours as well as elimination of parking spaces along roadway during construction, however, every effort will be made to minimize disturbances. Access to driveways may be obstructed for certain work, in these cases advanced notice will be provided. Noise from construction equipment can be expected during working hours. 

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

KINGS PARK SEWER CONSTRUCTION - SCHEDULE 07/22/2024 - 08/02/2024

Final paving restoration has been completed on all of Lawrence, Bowman, Yale, Squire, and St. Johnland. No further work is planned on these roads.

 

Plans for week of 7/22:

The Contractor plans to continue daytime excavation and pipe installation in the grass in front of Smithtown Parks Department, just south of Main Street, with minimal impact to Main Street traffic.

 

Plans for week of 7/28:

Nighttime excavation in Main Street is expected to restart Sunday night, 7/28, starting in Main Street at Kings Park Blvd. and progressing west towards Church and Pulaski. The work will involve excavation down the middle of Main Street for the installation of gravity sewer main pipes between the manholes, as well as lateral pipes towards curb lines.

 

Nightwork hours will be between 10:00 pm and 6:00 am. Nightwork in 25A will occur from Sunday - Thursday nights. 

Please note all pavement patches and trench restoration is temporary. The Contractor is working on trench restoration and all impacted roads will be repaved from curb-to-curb before final completion. If you notice a pothole or other issue, please contact us at (631) 393-4994.

You can expect periodic inconvenience due to equipment movement, material transport and trench excavation. There may be periodic road/lane closures and detours as well as elimination of parking spaces along roadway during construction, however, every effort will be made to minimize disturbances. Access to driveways may be obstructed for certain work, in these cases advanced notice will be provided. Noise from construction equipment can be expected during working hours. 

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

KINGS PARK SEWER CONSTRUCTION - SCHEDULE 6/24/2024 - 07/5/2024

Night work in Main Street is planned to be continued this week, Sunday through Thursday nights, from about 10 pm until 6 am each day.  The work week will end Friday
morning about 6 am.  
Nighttime excavation in Main Street will continue from west of Pulaski Road to Park Ave. This work phase will continue as last week, with excavation down the middle of Main Street for the installation of gravity sewer main pipes between the manholes, as well as lateral pipes towards curb lines.
Mid-week it is planned to install manholes in the Smithtown Parks Dept. Driveway and grass area immediately south of Main Street.  This excavation will cross the sidewalk, but have minimal impact in Main Street.
Minimal to no work is planned during daytime hours this week.

 

Nightwork hours will be between 10:00 pm and 6:00 am. Nightwork in 25A will occur from Sunday - Thursday nights. 

Please note all pavement patches and trench restoration is temporary. The Contractor is working on trench restoration and all impacted roads will be repaved from curb-to-curb before final completion. If you notice a pothole or other issue, please contact us at (631) 393-4994.

You can expect periodic inconvenience due to equipment movement, material transport and trench excavation. There may be periodic road/lane closures and detours as well as elimination of parking spaces along roadway during construction, however, every effort will be made to minimize disturbances. Access to driveways may be obstructed for certain work, in these cases advanced notice will be provided. Noise from construction equipment can be expected during working hours. 

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

KINGS PARK SEWER CONSTRUCTION - SCHEDULE UPDATE #14 6/3/2024 - 06/14/2024

Excavation work is scheduled to continue in Main Street between Park Ave. and Church Street this week.  One lane of traffic in each direction will be maintained on Main Street, with very short-term stoppages for equipment movement.   Plans for Monday are for excavation in the center of the intersection of Main and Church Street, and excavation in Main Street west of Renwick.  The rest of the week excavations will be made in Main Street from Henry, Renwick, Thompson, and continuing westward along Main Street. On Tuesday, the first 100 feet of Henry street will be closed.

 

Night work in 25A between Lawrence Road and Park Avenue will begin shortly. Nightwork hours will be between 10:00 pm and 6:00 am. Nightwork in 25A will occur from Sunday - Thursday nights. 

Please note all pavement patches and trench restoration is temporary. The Contractor is working on trench restoration and all impacted roads will be repaved from curb-to-curb before final completion. If you notice a pothole or other issue, please contact us at (631) 393-4994.

You can expect periodic inconvenience due to equipment movement, material transport and trench excavation. There may be periodic road/lane closures and detours as well as elimination of parking spaces along roadway during construction, however, every effort will be made to minimize disturbances. Access to driveways may be obstructed for certain work, in these cases advanced notice will be provided. Noise from construction equipment can be expected during working hours. 

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

KINGS PARK SEWER CONSTRUCTION - SCHEDULE UPDATE #13 5/6/2024 - 05/24/2024

Week of 5/6: Trench restoration on the following roads: Church Street Meadow Road, Renwick Ave, Pulaski Road, Dawson Avenue, Henry Street, Thompson Street, Park Drive, and Stattel Drive. 

Week of 5/13: Trench restoration on the following roads: Church Street Meadow Road, Renwick Ave, Pulaski Road, Dawson Avenue, Henry Street, Thompson Street, Park Drive, and Stattel Drive. 

Trench restoration work will occur during daytime hours. (7:00 am - 3-30 pm)

Night work in 25A between Lawrence Road and Park Avenue will begin on May 12, 2024. Nightwork hours will be between 10:00 pm and 6:00 am. Nightwork in 25A will occur from Sunday - Thursday nights. 

Please note all pavement patches and trench restoration is temporary. The Contractor is working on trench restoration and all impacted roads will be repaved from curb-to-curb before final completion. If you notice a pothole or other issue, please contact us at (631) 393-4994.

You can expect periodic inconvenience due to equipment movement, material transport and trench excavation. There may be periodic road/lane closures and detours as well as elimination of parking spaces along roadway during construction, however, every effort will be made to minimize disturbances. Access to driveways may be obstructed for certain work, in these cases advanced notice will be provided. Noise from construction equipment can be expected during working hours. 

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

KINGS PARK SEWER CONSTRUCTION - SCHEDULE UPDATE #12 04/8/2024 - 04/26/2024

Week of 4/15: Sewer Testing on Lawrence, Bowman, and Squire. Pavement and trench restoration on Lawrence, Bowman and Squire. 

Week of 4/22: Testing on gravity sewers on Church Street, Henry Street and Meridian Avenue. Pavement and trench restoration on Lawrence, Bowman and Squire. 

Night work in 25A between Lawrence Road and Park Avenue will begin in May 2024. Nightwork hours will be between 10:00 pm and 6:00 am. 

Work will generally be centered at the location of structures.

Please note all pavement patches and trench restoration is temporary. The Contractor is working on trench restoration and all impacted roads will be repaved from curb-to-curb before final completion. If you notice a pothole or other issue, please contact us at (631) 393-4994.

You can expect periodic inconvenience due to equipment movement, material transport and trench excavation. There may be periodic road/lane closures and detours as well as elimination of parking spaces along roadway during construction, however, every effort will be made to minimize disturbances. Access to driveways may be obstructed for certain work, in these cases advanced notice will be provided. Noise from construction equipment can be expected during working hours (7:00 am – 3:30 pm). 
 

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

KINGS PARK SEWER CONSTRUCTION - SCHEDULE UPDATE #11 03/18/2024 - 03/29/2024

Week of 3/18: Sewer Testing on Indian Head Rd and Meadow Road West. Cleanout installation on Bowman, Lawrence and Squire. 

Week of 3/25: Testing on gravity sewers on Church Street, Henry Street and Meridian Avenue. Trench Restoration will begin on Bowman, Lawrence and Squire. 

Work will generally be centered at the location of structures.

You can expect periodic inconvenience due to equipment movement, material transport and trench excavation. There may be periodic road/lane closures and detours as well as elimination of parking spaces along roadway during construction, however, every effort will be made to minimize disturbances. Access to driveways may be obstructed for certain work, in these cases advanced notice will be provided. Noise from construction equipment can be expected during working hours (7:00 am – 3:30 pm). 
 

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

KINGS PARK SEWER CONSTRUCTION - SCHEDULE UPDATE #10 03/04/2024 - 03/15/2024

Work over the next two weeks will be scattered. Manholes and sewer testing will be performed on Pulaski Rd, Henry Street, Meridian Ave, and Indian Head Road. Simultaneously, work will continue to finalize structure installations on Bowman, Lawrence, and Squire. Work will generally be centered at the location of structures.

You can expect periodic inconvenience due to equipment movement, material transport and trench excavation. There may be periodic road/lane closures and detours as well as elimination of parking spaces along roadway during construction, however, every effort will be made to minimize disturbances. Access to driveways may be obstructed for certain work, in these cases advanced notice will be provided. Noise from construction equipment can be expected during working hours (7:00 am – 3:30 pm). 
 

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

KINGS PARK SEWER CONSTRUCTION - SCHEDULE UPDATE #9 02/19/2024 - 02/23/2024

No work scheduled this week.

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

KINGS PARK SEWER CONSTRUCTION - SCHEDULE UPDATE #8 02/13/2024

No work today due to snow.

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

KINGS PARK SEWER CONSTRUCTION - SCHEDULE UPDATE #7 (02/05/24 - 02/16/24)

This week there is one road closure planned. The northern 200’ of Renwick will be closed Tuesday and Wednesday for manhole installation. There will be manhole installation and lateral pipe installation work in Indian Head Road, Henry, Thompson, Meridian, and Pulaski Roads, but these will not require closing these roads.  Alternating two-way traffic will be allowed during the work.
 

You can expect periodic inconvenience due to equipment movement, material transport and trench excavation. There may be periodic road/lane closures and detours as well as elimination of parking spaces along roadway during construction, however, every effort will be made to minimize disturbances. Access to driveways may be obstructed for certain work, in these cases advanced notice will be provided. Noise from construction equipment can be expected during working hours (7:00 am – 3:30 pm). 

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

KINGS PARK SEWER CONSTRUCTION - SCHEDULE UPDATE #6 (01/08/23 - 01/19/23)

The Contractor is starting installation of gravity sewer mains on Meadow Road West between 1st Avenue and Indian Head Road.  

You can expect periodic inconvenience due to equipment movement, material transport and trench excavation. There may be periodic road/lane closures and detours as well as elimination of parking spaces along roadway during construction, however, every effort will be made to minimize disturbances. Access to driveways may be obstructed for certain work, in these cases advanced notice will be provided. Noise from construction equipment can be expected during working hours (7:00 am – 3:30 pm). 

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

KINGS PARK SEWER CONSTRUCTION - SCHEDULE UPDATE #5 (12/04/23 - 12/15/23)

The Contractor has starting installation of gravity sewer mains on Church Street. Work has begun North of Old Dock and will be continuing South toward Main Street. 

You can expect periodic inconvenience due to equipment movement, material transport and trench excavation. There may be periodic road/lane closures and detours as well as elimination of parking spaces along roadway during construction, however, every effort will be made to minimize disturbances. Access to driveways may be obstructed for certain work, in these cases advanced notice will be provided. Noise from construction equipment can be expected during working hours (7:00 am – 3:30 pm). 

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

KINGS PARK SEWER CONSTRUCTION - SCHEDULE UPDATE #4 (11/06/23 - 11/27/23)

The Contractor is continuing installation on Yale Place and Bowman Lane. From Bowman installation will be progressing on Squire Lane and onto St. Johnland Road. During working hours a detour has been established. Please note local traffic and buses will still have access to roadway as needed.

 

Please note there will be now work occurring the week of November 20th. 
 
You can expect periodic inconvenience due to equipment movement, material transport and trench excavation. There may be periodic road/lane closures and detours as well as elimination of parking spaces along roadway during construction, however, every effort will be made to minimize disturbances. Access to driveways may be obstructed for certain work, in these cases advanced notice will be provided. Noise from construction equipment can be expected during working hours (7:00 am – 3:30 pm). 

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

KINGS PARK SEWER CONSTRUCTION - SCHEDULE UPDATE #3 (10/23/23 - 11/03/23)

The Contractor will continue to progress installation North on Lawrence Road between Boxwood Drive and Yale Place. During working hours a detour has been established. Please note local traffic and buses will still have access to roadway as needed.

 
You can expect periodic inconvenience due to equipment movement, material transport and trench excavation. There may be periodic road/lane closures and detours as well as elimination of parking spaces along roadway during construction, however, every effort will be made to minimize disturbances. Access to driveways may be obstructed for certain work, in these cases advanced notice will be provided. Noise from construction equipment can be expected during working hours (7:00 am – 3:30 pm). 

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

KINGS PARK SEWER CONSTRUCTION - SCHEDULE UPDATE #2 (10/09/23 - 10/20/23)

Please note there will be no work in roadway on Monday 10/09 in observance of Columbus Day. Force main installation will continue on Tuesday 10/10. The Contractor will continue to progress installation North on Lawrence Road between 25A and Boxwood Drive.

 
You can expect periodic inconvenience due to equipment movement, material transport and trench excavation. There may be periodic road/lane closures and detours as well as elimination of parking spaces along roadway during construction, however, every effort will be made to minimize disturbances. Access to driveways may be obstructed for certain work, in these cases advanced notice will be provided. Noise from construction equipment can be expected during working hours (7:00 am – 3:30 pm). 

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

KINGS PARK SEWER CONSTRUCTION - SCHEDULE UPDATE #1 (9/25/23 - 10/06/23)

Starting on Tuesday 9/26 through Wednesday 9/27 the Contractor will begin saw cutting the roadway on Lawrence Road, Bowman Lane,  and Yale Lane  between 25A and St. Johnland Road. On Thursday 9/28 the Contractor will begin excavation work for force main installation. Installation will begin just North of the Intersection of Lawrence Road and NY-25A and will continue up to Boxwood Drive. This segment of force main is estimated to be completed by Friday, 10/6. 
 
You can expect periodic inconvenience due to equipment movement, material transport and trench excavation. There may be periodic road/lane closures and detours as well as elimination of parking spaces along roadway during construction, however, every effort will be made to minimize disturbances. Access to driveways may be obstructed for certain work, in these cases advanced notice will be provided. Noise from construction equipment can be expected during working hours (7:00 am – 3:30 pm). 

Have Questions or Comments?

Email: kingsparksewers@suffolkcountyny.gov

Phone: (631) 393-4994

THE KINGS PARK SEWER EXPANSION

Suffolk County and the Town of Smithtown are thrilled to announce that the highly anticipated sewer line construction into Downtown Kings Park is set to break ground in the Summer of 2023. 

 

The installation of sewers in Downtown Kings Park, will make way for new or expanded commercial growth like restaurants, cafes, bars, and mixed use development. Furthermore, as we’ve historically witnessed in surrounding areas, the project will increase property values within the community. 

View & Download the Kings Park Downtown Sewers Phasing Map